Software Engineering
Unit wise questions
Unit 5 – Project Planning and Management
Topic – the project management spectrum
1.
Explain the role of people, product and process in
project management.
(May
2011 – 6 Marks, May 2013 – 8 Marks)
2. Explain the
term people and the product of management spectrum.
(May 2012 – 8 Marks)
Topic – People
3.
What are the categories of stakeholders? What are the
characteristics of effective project manager? (May 2014 – 8 Marks)
Topic – Software Measurement
4.
What are the attributes of effective software metrics?
(May
2014 – 4 Marks)
5.
What is object oriented metric? (May 2014 – 6 Marks)
6.
Explain size oriented metric. What data should we
collect to derive size oriented metric?
(May 2014 – 4 Marks)
7.
Differentiate and explain size and function oriented
metrics. (May 2011 – 6 Marks)
8.
Explain the FP based estimation technique. (May 2011 – 6 Marks)
9.
Explain metrics for object oriented projects. (Dec 2011 – 8 Marks)
10. How do you
calculate FP and how it Is used to in estimation of a software project? (May 2013 – 8 Marks)
11. Explain the
computation of function point (FP) metric for project estimation with an
example. (Dec 2013 – 8 Marks)
12. What is LOC
based estimation? Explain with an example. (Dec
2013 – 8 Marks)
Topic – Metrics for Software Quality
13. Explain in
detail – defect removal efficiency. (May
2014 – 4 Marks)
14. How do you
measure software quality in terms of maintainability and integrity?
15. (May 2014 – 6 Marks)
16. Explain
defect removal efficiency as a metric for project and process.
(Dec 2012 – 8 Marks)
17. Explain any
four quality measure of software. (Dec 2013 – 8 Marks)
Topic – Decomposition
18. What is
software project estimation? How use cases are used in estimation?
(May 2011 – 6 Marks)
19. What is LOC
based estimation? Explain with a suitable example. (Dec 2011 – 8 Marks)
20. What do you
mean by software project estimation? Explain the process based estimation with
an example. (Dec 2012 – 8 Marks)
Topic – Empirical Estimation Models
21. Explain
COCOMO II model. (Dec 2011 – 8 Marks)
22. Explain
COCOMO model for project estimation.
(Dec 2013 – 8 Marks)
Topic – Project Scheduling
23.
What is project scheduling? What are the basic
principles of project scheduling?
(May
2012, 8 Marks)
Topic – Defining a task set for the software project
24. What
is a task network in project scheduling? Explain with an example. (May 2011, 8 Marks)
25. What
is a task network? How it is used in scheduling of software project?
(May
2011, Dec 2013 – 8 Marks)
Topic – Time Line Chart
26.
What is time line chart? How it is used in
scheduling of a software project? (Dec
2012 – 8 Marks)
Topic – Tracking the schedule
27. Discuss
the techniques used in tracking the project schedule. (Dec 2012 – 8 Marks)
Topic – Earned Value Analysis
28.
Explain earned value analysis in project
scheduling. (May 2011 – 8 Marks)
Topic – Risk Management
29. What
are the types of risks? Explain in brief. (May
2014 – 6 Marks)
Topic – Risk Identification
30. Explain
the risk identification and assessment process for a software project.
(May
2013, Dec 2013 -8 Marks)
Topic – Risk Projection
31. How
risk projection is carried out in risk table? (May 2011 – 8 Marks)
Topic – Risk Mitigation, Monitoring and Management
(RMMM)
32. What
is risk mitigation, monitoring and management (RMMM)? Write a note on it?
(May
2012 – 10 Marks)
33. Write
short note on RMMM. (May 2014 – 5 Marks)